+91-9818062147

GD800D-LS HDD Machine in Pipeline Crossing Project in Wuzhong City Ningxia Province

Project Name: Pipeline Crossing Project

Project location:Wuzhong City Ningxia Province

Pipe Specification:Φ813mm Steel Pipe

Construction Equipment:GD800D-LS HDD Machine

Crossing length:360m

Soil condition: Rock mass